Location: Southern face of Mt Dandenong

Status: Building - Not online Yet !
Linked to <node>, covering local area from Hampton Park to Beconsfield using <Waveguide>

SSID: to be <jaa.melbournewireless.org.au>

Connecting...
Set your SSID to jaa.melbournewireless.org.au and contact melb_ap for more information.







Node Log







7/3/09 - Did site survey and established LOS to GXT and ICQ - yah !

14/3/09 - Node build planning underway. Have procured Wind Turbine / batteries for power

3/5/09 - Node installation has started, the pole is concreted in and the cabinet base done, with many thanks to Will, David, John, Adam and Mike for their assistance in wresting the pole into place !

7/5/09 - Have the turbine almost ready for install, will hopefully visit this weekend to continue commissioning works.

10/5/09 - With many thanks to Michael, the turbine and enclosure are all mounted. The prop will go on once the electrics are done & tested.

12/5/09 - Most of the electrics & breakers for the turbine have been completed.

13/5/09 - Electrics completed and tested ok. Prop now on and turbine seems to be working. Further testing required.
have also setup the weather station and an uplink ap. Uplink almost online, will happen soon !










Equipment


This node will be a Green node running off wind power

Planned Equipment;

Wind Turbine & Associated Batteries / Power Management.

2.4Ghz Wave guide for Southern coverage of Hampton Park to Emerald ?

5.8Ghz Uplink to MW network connection ?



We have procured a 300W Jaycar wind turbine and some
decommissioned batteries to suit at this stage.










{http://www.melbournewireless.org.au/files/Images/picture.png Photo of node setup" alt="Node JAA Owner: melb_ap

Location: Southern face of Mt Dandenong

Status: Building - Not online Yet !
Linked to <node>, covering local area from Hampton Park to Beconsfield using <Waveguide>

SSID: to be <jaa.melbournewireless.org.au>

Connecting...
Set your SSID to jaa.melbournewireless.org.au and contact melb_ap for more information.







Node Log







7/3/09 - Did site survey and established LOS to GXT and ICQ - yah !

14/3/09 - Node build planning underway. Have procured Wind Turbine / batteries for power

3/5/09 - Node installation has started, the pole is concreted in and the cabinet base done, with many thanks to Will, David, John, Adam and Mike for their assistance in wresting the pole into place !

7/5/09 - Have the turbine almost ready for install, will hopefully visit this weekend to continue commissioning works.

10/5/09 - With many thanks to Michael, the turbine and enclosure are all mounted. The prop will go on once the electrics are done & tested.

12/5/09 - Most of the electrics & breakers for the turbine have been completed.

13/5/09 - Electrics completed and tested ok. Prop now on and turbine seems to be working. Further testing required.
have also setup the weather station and an uplink ap. Uplink almost online, will happen soon !










Equipment


This node will be a Green node running off wind power

Planned Equipment;

Wind Turbine & Associated Batteries / Power Management.

2.4Ghz Wave guide for Southern coverage of Hampton Park to Emerald ?

5.8Ghz Uplink to MW network connection ?



We have procured a 300W Jaycar wind turbine and some
decommissioned batteries to suit at this stage.










{http://www.melbournewireless.org.au/files/Images/picture.png Photo of node setup" />







Services



This node will provide an Uplink point and coverage
for the Narewarren / Berick / Hampton Park etc region.






Plans


It's also planned to provide an up link to Aurthurs Seat in the near future.





I intend to link up to NodeGXT

I intend to link up to NodeJNA

I intend to link up to NodeICQ




Problems



Still Sourcing equipment such as


Shopping List



Decent pole for turbine - maybe ex 6mtr power pole - Sourced

Some 3 Wire cable to connect to turbine (6 ish Mtr) - Sourced

Cat 5 & conduit to run up pole to bullet ap's - to pickup

Standoff vertical poles 35mm ish to give mounting point for antennas.

6mtr solid pole - Sourced

Monitoring / routing access point - will use wl500gP with weather station
& picaxe connection for battery monitoring - Have wl500gp just need to program / test - need to make picaxe monitoring circuit - design logic mostly done


Wind turbine - Have

Battery Pack - Have

Main Enclosure - Have - just needs prep




Backbone


Version 5 (old) modified Mon, 26 Jul 2021 12:49:29 +0000 by melb_ap
[EditText] [Spelling] [Current] [Raw] [Code] [Diff] [Subscribe] [VersionHistory] [Revert] [Delete] [RecentChanges]
> home> about> events> files> members> maps> wiki board   > home   > categories   > search   > changes   > formatting   > extras> site map

Username
Password

 Remember me.
>

> forgotten password?
> register?
currently 0 users online
Node Statistics
building132
gathering192
interested515
operational242
testing216